English中文简体

News Center

2020年度北美最佳修复项目荣誉奖:SAWS多污水处理系统配套2A 2021-05-10
在美国许多大型都市区,主要的下水道干线位于大型流域,在那里大量降雨会造成严重破坏。在这些城市中,控制下水道流量对于管理系统容量问题至关重要。德克萨斯州圣安东尼奥市是美国的第七大都市之一,它们面临着老化和基础设施紧张的双重挑战。
圣安东尼奥供水系统(SAWS)为地域分散的人口提供服务,超过180万人,并且在整个圣安东尼奥地区,比克萨尔县以及麦地那和阿塔斯科萨县的部分地区拥有超过411,000名废水处理客户。 EPA同意法令计划确定了大都会中的关键管道,以进行强制性维修。该项目被命名为“ SAWS多污水处理系统套装2A”项目,该项目包括修复六个不同的部分,现有管道总计约有14,900轴线英寸。除了使用现场固化管(CIPP)进行老化管的更新外,该项目还包括对24至72英寸范围内的重力下水道主管道进行维修,并对分布在七个区域的几座大型混凝土结构进行部分拆除/维修/替换。


2020 Project of the Year Rehabilitation Honorable Mention: SAWS Multiple Sewershed Package 2A



In many large metroplexes throughout the United States, major sewer trunk lines are located in the large drainage basins where significant rain events can wreak havoc. In these cities, controlling sewer flow is critical to managing system capacity issues and potential backups. The City of San Antonio, Texas, the seventh largest city in the United States, is one of those metroplexes and they faced the dual challenge of an aging and stressed infrastructure.


The San Antonio Water System (SAWS) serves a geographically dispersed population of more than 1.8 million people and more than 411,000 wastewater customers spread across the greater San Antonio area, within Bexar County and parts of Medina and Atascosa counties. The EPA consent decree program identified critical pipelines in the metroplex for mandated repairs. Named the SAWS Multiple Sewershed Package 2A project, the undertaking of this project consisted of the rehabilitation of six different sections totaling approximately 14,900 lf of existing pipe. In addition to using cured-in-place pipe (CIPP) to renew the aging pipes, the project included repairs to gravity sewer mains ranging from 24 to 72 in. and the partial demolition/repair/replacement of several large concrete structures spread across seven separate sites.


Alone, this would be the largest CIPP project in San Antonio’s history. However, SAWS recognized the opportunity to concurrently update its flow management system with a new design. The project had significant logistical challenges with sections situated under & across golf courses, city parks, flood plains and residential neighborhoods. In addition, the engineer for this project, CDS Muery, developed a novel design to implement metal flow plates that could be easily installed or removed to control flow management, replacing the problematic mechanical gates within their respective structures.


Adding to the physical obstacles were complex bypass requirements. First, there was the concurrent bypass of parallel 54- and 66-in. lines. On its own that quantity of bypass is challenging, but midway through the project a separate capacity project (a non-rehab project that consists of the upsizing of existing lines or the installation of new and additional pipeline) came online upstream with the potential to add 19 million gallons a day of additional flow rushing into the lines. SAK stepped in and developed a plan to accommodate the flows without any additional cost to SAWS, managing the flow without issues.
Why Project is Outstanding:

In addition to the sheer size of the CIPP rehabilitation project and the unique challenges faced during the job, this is the first project of its kind that utilized a flow-plate design for managing flows and the first set of structures to incorporate that design. The introduction of the new flow plate design created a more efficient method to manage the massive amounts of flow funneling daily through San Antonio’s sewer system.
The old flow structures had mechanical gates that over time became inoperable. The outdated gates required significant maintenance and would often freeze, causing their fragile stems (used to raise and lower the gates) to snap when operated. This crippled the ability of SAWS to shift the heavy flows to different pipelines or basins and, as a result, left them powerless to take lines out of service. Oftentimes, the broken gates were just left unutilized and routine repairs turned into costly ones that required pulling the lid on the structure and bypassing the lines.


By using a flow plate design, all seven structures became accessible for diverting increased flows, significantly increasing SAWS ability to manage the overburdened lines. If individual pipelines needed isolation, the SAWS teams have the ability to do that, as well. Most importantly, this investment in a new setup created a tremendous advantage over the old system because it is virtually maintenance free. The flexibility of the new flow plate design also gave SAWS the ability to interchange plates across all of the structures, creating a substantial improvement and reduction in maintenance.


As a direct result of the success of the new flow plate design solution, other U.S. metroplexes with similar issues are planning to incorporate the design. This was the first time this technology had ever been used for SAWS and it likely won’t be the last.


In addition to accommodating the unexpected flows, SAK crews were tasked with tackling four separate unplanned emergency projects:
1 – A sewer collapse near an apartment complex along a Texas Department of Transportation right of way.
2 – A large void on a 33-in. line inside of an easement.
3 – A siphon that travels under the San Jacinto River.
4 – A 24-in. line that with voids requiring rehabilitation of the line sooner than SAWS had originally planned.



News Center Sponsors List Media Partners Download Problem Links
Num:沪ICP备10040940号-5 TEL:86-21-54791130 FAX:86-21-54791130 Mail:ITTC@CSTT.ORG, Copyright 2010-2022 SHKEXI.COM. All Rights Reserved